Start with a load list
Generator sizing starts with a list of everything that plugs in, when it runs, and where it sits on the site. Group it like this:
- Audio: amplifiers, powered speakers, consoles, backline.
- Lighting: moving lights, washes, hazers, followspots.
- Video: LED walls, processors, cameras, streaming.
- Vendors and support: food trucks, bars, refrigeration, production office, restroom trailers, site lighting.
Do not size from the stage alone. One festival power planning guide estimates that stages use only about a third of total site power, with lighting the biggest share of what the stage draws.
Rough numbers for common gear
- Lighting: a common LED wash light, the Martin MAC Aura XB, is rated at 400 W. Thirty of them is about 12 kW.
- LED walls: outdoor panels such as the Absen X5 are rated around 185 to 260 W per square meter on average, with peaks around 555 to 760 W per square meter at full white depending on the version. Plan for the peak.
- Audio: amplifier makers publish current draw at "1/8 power," which represents typical program with occasional clipping. Use those figures, not the maximum rating on the front panel.
- Food trucks: roughly 2 to 5 kW for a light setup, 6 to 12 kW for a standard truck, and 12 to 20 kW or more for a heavy kitchen. Ask each vendor.
Rough generator sizes by event scale
Starting points only. Lighting design, LED wall size, vendors and run time change the real number.
- Small event (DJ, speeches, compact PA, a few lights): about 10 to 20 kW. Our 25 kVA MultiQuip (about 20 kW prime) covers most of these.
- Mid-size concert or corporate show (line array, lighting rig, modest LED wall): about 30 to 80 kW, often split between a 45 kVA unit (about 36 kW prime) for audio and a second unit for lighting and video.
- Festival main stage: often 100 kW or more for the stage alone. Our 125 kVA unit (about 100 kW prime) with 600 A distribution fits here, with separate generators for vendors.
Bigger is not automatically better. Generators run most efficiently around 70 to 80 percent load, and a UK study found 60 percent of festival generators were more than double the size needed.
Why audio gets its own generator
Whenever the show allows it, we put sound on its own generator and distribution. Lighting, LED walls and vendor equipment such as fryers, compressors and refrigeration switch on and off all day. Keeping audio separate:
- lowers the risk of hum and buzz in the PA,
- means a tripped breaker at a food truck cannot cut the show,
- makes loads easier to track and balance during the event.
Bars and vendors with all-night refrigeration are often better on their own smaller generator, so the stage generator can shut down after the show.
Safety basics
- Code: Florida enforces the National Electrical Code through the Florida Building Code. NEC Article 525 covers temporary power at fairs, festivals and similar events.
- GFCI: 125 V, 15 and 20 A receptacles the public can reach need GFCI protection.
- Cables: use extra-hard-usage, wet-rated cable, cover it in walkways, and keep connectors out of audience paths unless guarded.
- Placement: keep generators away from crowds, doors and air intakes because of carbon monoxide. Miami-Dade Fire Rescue requires generators to be at least 20 feet from tents.
- Fuel: shut down and let the engine cool before refueling, and plan fuel for the full run time.
Send us your schedule and load list, and we will quote the right generators and distribution for your event.
General guidance, not engineering or legal advice. Every site and permit is different; we confirm the details for your event when we quote it.